13th August - 3 and a half weeks into the renovation. The homogeneous flooring is done up. Cardboard sheets are still layed on the floor so it still doesnt look nice. Stainless steel piping is complete and the toilet bowls and sinks have been installed. Somehow i noted that the shower stand in the MBR is not placed in the position i wanted. Hiaz... my fault for not communicating to the contractor earlier. One more unfortunate thing happened... not sure if it has to do with 13th. The contractors installed in storage heater and we were told that it is leaking! Gosh! Gotta get a new one :(
14th August - We bought lights from Chuan Huat and Dream Lights over the weekend. Total damages of around $1k. Delivery is today. Cant wait to have them installed soon :)
KH went to Hoe Kee at IMM again to get the storage heater. Another damage of $220+.
15th August - The electician are coming down to do rewiring. We went to inspect on the work around 9 plus and the electricians are still there testing the switches.
The flower common bath room without the accessories
14th August - We bought lights from Chuan Huat and Dream Lights over the weekend. Total damages of around $1k. Delivery is today. Cant wait to have them installed soon :)
KH went to Hoe Kee at IMM again to get the storage heater. Another damage of $220+.
15th August - The electician are coming down to do rewiring. We went to inspect on the work around 9 plus and the electricians are still there testing the switches.
The flower common bath room without the accessories